More than 780 kilometers of highways and expressways are being built in Romania.
According to data from the National Road Infrastructure Management Company (CNAIR), 781.38 kilometers of highways and expressways are currently under construction in Romania, of which 263.43 kilometers are in the planning phase and 517.95 kilometers are in the construction phase.
Development of the A0 highway: - Section 3 between South Bragadiru and Joiţa (17.965 km) is under construction. - Section 1 between North Joiţa and Corbeanca (17.5 km) in the planning phase. - Section 3 between North Afumaţi and Pantelimon (8.60 km) is under construction. - Section 4 between North Pantelimon and Glina (4.47 km) is also under construction.
The A1 highway projects: - The Bojca-Cornetu (31.33 km) and Cornetu-Tigveni (37.40 km) sections are in the planning stage. - The Tigveni-Curtea de Argeş (9.86 km) and Curtea de Argeş-Piteşti (30.35 km) sections are under construction. - The E and D sections of the highway section 2 between Lugos and Déva are also being built, which are 9.13 km long.
Developments of the Northern Transylvanian (A3) highway: - The Magyarnádas-Nádasszentmihály (16.80 km), Nádasszentmihály-Magyarzsombor (13.26 km) and Magyarzsombor-Vaskapu (12.24 km) sections are under construction. - The section between Berettyószéplak and Bisztraterebes (26.35 km) is in the planning phase. - The Bisztraterebes-Bihar section received a planning commission.
Development of the A7 motorway: - 320 km long between Ploieşti and Paşcani is under construction. The A8 sections that are currently being planned: - The section between Marosvárhely and Nyárádszereda (24.4 km). - Section between Leghin and Târgu Neamţ (29.9 km). These developments significantly contribute to the modernization of Romania's transport infrastructure and the economic development of their surroundings.